What's due by November 1, 2027, and what's due now

The LCRI deadlines, the 2024 rules that apply until then, and the yearly cycle after.

Last reviewed against the sources linked in the text.

EPA's Lead and Copper Rule Improvements (LCRI) apply to community water systems and non-transient non-community water systems: the systems that serve homes, and the ones that serve the same people every day, like schools and workplaces. The compliance date is November 1, 2027. (40 CFR 141.80(a)(3))

Due by November 1, 2027

  • Baseline service line inventory. Every service line, the system's side and the customer's side, classified as lead, galvanized requiring replacement (GRR), non-lead, or lead status unknown, plus lead connectors. (40 CFR 141.84(a))
  • Service line replacement plan, if any line is lead, GRR, or unknown. It has to be made public. (40 CFR 141.84(c))
  • Customer notices to everyone served by a lead, GRR, or unknown line, no later than 30 days after the baseline inventory is completed. (40 CFR 141.85(e))

Due now, before 2027

Until the compliance date, systems follow the inventory and notice rules as they were written on July 1, 2024 (the Lead and Copper Rule Revisions). (40 CFR 141.80(a)(4)(i)) Under those rules the initial inventory was due October 16, 2024; notices go out within 30 days of completing the inventory and are repeated every year; and each year by July 1 the system shows the State that the previous year's notices were delivered. (40 CFR 141.90(f)(4), July 1, 2024 text)

After 2027

  • Replace every lead and GRR line within ten program years. Program year 1 runs from November 1, 2027 to December 31, 2028; later program years are calendar years, so the tenth ends December 31, 2037. (40 CFR 141.84(d)(4)–(5))
  • Keep a cumulative average replacement rate of at least 10% a year, checked from the end of program year 3. (40 CFR 141.84(d)(5)) Our replacement pace calculator shows the numbers for your system.
  • Every January 30, starting in 2029: an inventory update, a plan update or certification, a lead connector certification, and a certification that the previous year's notices were delivered. (40 CFR 141.90(e)–(f))
  • Notices again within 30 days after each annual inventory update deadline, for as long as a line stays lead, GRR, or unknown. (40 CFR 141.85(e)(2))
  • Validate a random sample of non-lead lines by December 31, 2034. (40 CFR 141.84(b)(5))

States can set their own dates or add requirements. Check with your State drinking water program, or use our What's due tool to see these dates for your system.

This guide explains the rules in plain language; it isn't legal advice. Your State's drinking water program has the final word on your system.